OCEANSIDE HIGH SCHOOL

Proyectos completados

MEASURE W

OHS Field
  • OHS - Track & Field Replacement

    Actual Start: Jul 2022 Bond: Measure W

    Actual Finish: Sep 2024 Budget: $1,861,605.74

    Brand new field turf replaced the existing, aging field. The track surface was grinded down to an even grade, and broadcast in the school colors and striped to standards. The long jump pit covers and pole vault footings were replaced and runways also received the refurbished surfacing.
20231128_112743
  • OHS - Shade Structure

    Actual Start: Jul 2022 Bond: Measure W

    Actual Finish: Mar 2024 Budget: $194,402.00

    This project brought the addition of two new 20' x 30' fabric shade structures at the center of the campus lunch pavillion.

PROPOSITION H

20230803_121435
  • OHS - Gym Bleachers

    Actual Start: Dec 2022 Bond: Proposición H

    Actual Finish: Mar 2024 Budget: $510,061.79

    The scope of work consisted of the removal of the aging bleachers from the gymnasium and the replacement with new telescoping bleachers including necessary electrical upgrades. Additional improvements for ADA compliance were made in the surrounding areas.
IMG_0784
  • OHS - Gym Windows & Fans

    Actual Start: Jan 2022 Bond: Proposición H

    Actual Finish: Feb 2023 Budget: $426,512.93

    The project involved the removal and replacement the existing clerestory windows on the saw-tooth roof and installation of two big fans inside of gym.
IMG_0544
  • OHS - Gym Roof & HVAC Repairs

    Actual Start: Mar 2020 Bond: Proposición H

    Actual Finish: Jan 2022 Budget: $1,526,461.31

    This project consisted of the replacement the existing roof with a new membrane over the main gym and the stage areas. Additionally, two HVAC units were replaced at the lobby, as well as three non-functioning exhaust fans for heat capable fans.
OHS_PArts-1536x1024
  • OHS - Performing Arts Center

    Actual Start: Dec 2013 Bond: Proposición H

    Actual Finish: Feb 2019 Budget: $24,198,462.04

    In addition to a 502-seat main theater, the PAC includes a black box theater, drama classrooms, recording studio, scene shop, and green room. The indoor-outdoor lobby with its concession area doubles as an event venue, as does the new plaza on the west side of the building. The main theater is equipped with sophisticated audio/visual, lighting and acoustical systems that can facilitate a wide variety of performances and events.
ohs-music-bldg
  • OHS - Modernization, Music

    Actual Start: Feb 2010 Bond: Proposición H

    Actual Finish: Feb 2013 Budget: $3,848,715.00

    El edificio de música existente, construido en 1955, fue reemplazado por un edificio nuevo, más grande, de dos salones, mejorado acústicamente para acomodar los programas de la banda y el coro. El nuevo edificio de música también ofrece áreas de práctica y almacenamiento de instrumentos, baños para estudiantes y personal y espacio para oficinas.
ohs-career
  • OHS - New, Career Tech

    Actual Start: Jun 2009 Bond: Proposición H

    Actual Finish: Aug 2012 Budget: $4,648,005.08

    Se agregaron dos edificios de aulas al campus para permitir la expansión del programa educativo de tecnología profesional. Las nuevas instalaciones fueron diseñadas específicamente para que los estudiantes reciban ciencias de la salud y oficios de construcción, carreras y capacitación técnica. Se agregó un nuevo estacionamiento de 141 espacios adyacente a los edificios para proporcionar estacionamiento en la esquina suroeste del campus.
OHS Athletic Field 2009
  • OHS - Athletic Field

    Actual Start: Apr 2009 Bond: Proposición H

    Actual Finish: Sep 2010 Budget: $8,062,883.48

    The high school's stadium received major upgrades during the short time span between the end of the 2009 and the beginning of the 2010 football season, including a new synthetic turf athletic field and 9-lane track, the addition of over 2,500 grandstand seats on the home side with relocation of over 1,000 bleacher seats and a restroom building to the visitors’ side, a new fitness center with restrooms and locker room, a new ticket booth, and field lighting.

PROPOSITION G

  • OHS - Modernization, Gymnasium

    Actual Start: Aug 2002 Bond: Proposition G

    Actual Finish: Mar 2008 Budget: $7,092,711.00

    The renovation of the gymnasium, also included the conversion of the stage to PE classrooms and reconstruction of the girls' shower/locker area into department offices. New construction included a one-story front entrance addition and demolition of the existing boys' shower/locker area, replacing it with a two-story gymnasium addition.
OLYMPUS DIGITAL CAMERA
  • OHS - New, Science & Tech Bldg

    Actual Start: Dec 2000 Bond: Proposition G

    Actual Finish: Jun 2004 Budget: $13,633,075.05

    The new three-story Science and Technology building houses 30 classrooms and labs, four study rooms, rooftop astronomy viewing deck and two greenhouses.
OLYMPUS DIGITAL CAMERA
  • OHS - Modernization, Phase D

    Actual Start: Mar 2002 Bond: Proposition G

    Actual Finish: Feb 2004 Budget: $3,436,575.44

    Aging classroom buildings built in 1956, 1959, and 1965 housing 26 classrooms were modernized, providing students with an up-to-date learning environment.
OLYMPUS DIGITAL CAMERA
  • OHS - Modernization, Phase C

    Actual Start: Oct 2001 Bond: Proposition G

    Actual Finish: Jan 2003 Budget: $3,264,734.17

    Aging facilities including classroom buildings built in 1937, 1939, and 1970, housing 21 classrooms, were modernized providing students with an up-to-date learning environment.
OLYMPUS DIGITAL CAMERA
  • OHS - Modernization, Phase B

    Actual Start: Feb 2001 Bond: Proposition G

    Actual Finish: Sep 2002 Budget: $4,096,597.61

    Aging facilities including classroom buildings built in 1954, 1955, and 1959, housing 18 classrooms, the school library (1955) and the administration building (1956) were completely renovated.
OLYMPUS DIGITAL CAMERA
  • OHS - Modernization, Phase A

    Actual Start: Dec 2000 Bond: Proposition G

    Actual Finish: May 2002 Budget: $1,105,373.00

    Reconstruction and rehabilitation of main electrical power system. Alteration to existing buildings.