Alcance:
The modernization of Jefferson Middle School will consist of the following:
• Various building modernization
• Required ADA upgrades
• Required site infrastructure upgrades
• Project interim housing
• Exterior improvements and upgrades with special attention to redeveloping a main entry
• New construction of gym and multipurpose room with kitchen
Estado:
Bidding, Procurement, and Phase 1 Construction
Fuente de financiamiento:
Proposition H & Measure W
Estimación del proyecto:
$37,000,000
Tipo de proyecto:
Modernization and New Construction
Método de entrega:
Design Build
Inicio de construcción:
Summer 2024
Finalización dirigida:
Winter 2026