Palmquist Elementary School Safety & Security Pilot

agosto 29, 2024
Palmquist Rooms 67 8 7

Scope: This project consisted of the installation of the safety and security systems as part of the pilot programs at the Palmquist Elementary School and Chavez Middle School sites. Status: Complete Palmquist Rooms 67 8 7 Funding Source: Measure W Project Cost: $407,470.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: Winter 2023 […]

Chavez Middle School Safety & Security Pilot

agosto 29, 2024

Scope: This project consisted of the installation of the safety and security systems as part of the pilot programs at the Chavez Middle School Campus. Status: Complete Funding Source: Measure W Project Cost: $480,359.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: Winter 2023 Completion: Spring 2024

Claire Burgener ADA Ramp

agosto 29, 2024

Scope: This project consisted of the construction of a new exterior ADA compliant ramp, restripe the parking area, new curbs, and modifications to fencing at the Claire Burgener Academy campus. Status: Complete Funding Source: Proposition H Project Cost: $250,000.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: Winter 2023 Completion: Summer 2023

Upcoming Projects: Contractor Outreach, November 6, 2023

noviembre 13, 2023

OUSD and CCM/MAAS hosted an Upcoming Projects Contractor Outreach Event on November 6 2023.  The presentation and sign in sheets are available below. Contractor Outreach Presentation, 11-06-2023 Contractor Outreach, sign in sheet, 11-6-23

Oceanside High School Bleacher Replacement

septiembre 5, 2023

Scope: This project consisted of the removal of existing bleachers and replacing them with a new VersaTract telescopic bleacher system. The electrical was updated to meet the requirement of the new bleachers. Status: Complete Oceanside HS Gym Funding Source: Proposition H Project Cost: $566,000.00 Project Type: Renovation Delivery Method: Multi-Prime   Construction Start: Summer 2023 […]

Oceanside High School Track & Field Replacement

julio 31, 2023

Scope: This project consisted of the replacement of the running track and football field turf on the Oceanside High School Campus.  The project also consisted of ADA upgrades. Status: Complete OHS Field Funding Source: Measure W Project Cost: $1,673,515.00 Project Type: Modernization Delivery Method: Multiple-Prime   Construction Start: Summer 2023 Targeted Completion: Spring 2024

El Camino High School Shade Structure

septiembre 28, 2022

Scope: This project consisted of the construction of a new shade structure on the El Camino High School Campus. Status: Construction Funding Source: Measure W Project Cost: $194,401.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: Summer 2023 Completion: Fall 2023

Oceanside High School Shade Structure

septiembre 28, 2022

Scope: This project consisted of the construction of a new shade structure on the Oceanside High School Campus. Status: Complete OHS front of school Funding Source: Measure W Project Cost: $132,150.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: Summer 2023 Completion: Fall 2023

Ivey Ranch Elementary School Playgrounds & Shade Structure

septiembre 28, 2022
Ivey Ranch ES

Scope: This project consisted of the construction of new playground equipment and shade structure on the Ivey Ranch Elementary School Campus. Status: Complete Ivey Ranch ES Funding Source: Measure W Project Cost: $597,795.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: Summer 2023 Completion: Fall 2023

McAuliffe Elementary School Shade Structure

septiembre 28, 2022
cropped McAuliffe 2

Scope: This project consisted of the construction of a new shade structure on the McAuliffe Elementary School Campus. Status: Complete cropped McAuliffe 2 Funding Source: Measure W Project Cost: $223,000.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: Summer 2023 Completion: Fall 2023

Scroll al inicio