Upcoming Projects: Contractor Outreach, November 6, 2023

noviembre 13, 2023

OUSD and CCM/MAAS hosted an Upcoming Projects Contractor Outreach Event on November 6 2023.  The presentation and sign in sheets are available below. Contractor Outreach Presentation, 11-06-2023 Contractor Outreach, sign in sheet, 11-6-23

Reynolds Elementary School Campus Rebuild

junio 30, 2023

It has been determined that the soil’s condition at Reynolds Elementary is not suitable for the planned construction.  Several tests revealed soil liquefaction. Soil liquefaction is a loss of ground strength that causes the soil to temporarily behave like a liquid. During an earthquake this could cause buildings to sink and incur other damages.  After careful …

Reynolds Elementary School Campus Rebuild Read More »

Ditmar Child Development Center Improvements

septiembre 6, 2022

Scope: This project consisted of the placement of a modular building at Surfside Academy to house the Child Development Center.  Scope included, electrical, plumbing, paint, ceiling tiles, fire alarm and ADA ramps. Status: Complete Funding Source: Proposition H Project Cost: $315,000 Project Type: Modernization Delivery Method: Multiple-Prime Construction Start: Fall 2021 Completion: Fall 2022

Oceanside High School Special Education Classroom Improvements

septiembre 6, 2022

Scope: The scope of work will include upgrading the flooring, paint, ceiling tile, lights to LED, fix/or provide new plumbing and/or fixtures, paint and/or replace wall coverings, reconfigure electrical throughout classrooms, repair any HVAC item, upgrade case work and countertops and thermal insulation as needed. Status: Completed Funding Source: Proposition H Project Cost: $62,960.00 Project …

Oceanside High School Special Education Classroom Improvements Read More »

Oceanside High School Gym Improvements

septiembre 6, 2022

Scope: The scope of work will remove and replace the existing clerestory windows on the saw tooth roof and installation of two big fans inside of gym and site improvements. Status: Complete Funding Source: Proposition H Project Cost: $423,000.00 Project Type: Modernization Delivery Method: Prime Contractor Construction Start: Fall 2022 Completion: Spring 2023

Bond Overview & Contractor Outreach Event, August 22, 2022

agosto 11, 2022

OUSD and CCM/MAAS hosted a Bond Overview and Contractor Outreach Event on August 22, 2022.  The presentation and sign in sheets are available below. Contractor Outreach Presentation, 8-22-2022 Sign in sheet, 8-22-22

Bond Overview & Contractor Outreach Event, June 13, 2022

junio 22, 2022

OUSD and CCM/MAAS hosted a Bond Overview and Contractor Outreach Event on June 13, 2022.  The presentation and sign in sheets are available below. Contractor Outreach Presentation, 6-13-2022 Sign in sheet, 6-13-2022

Pablo Tac Groundbreaking Ceremony

junio 6, 2022

On June 6, 2022, OUSD and CCM/MAAS broke ground on the Pablo Tac Elementary School campus (formally San Luis Rey Elementary School).  The school was renamed to honor the indigenous scholar whose heritage & academic work to preserve the Luiseño language embodies the school’s values. In attendance were: Dr. Stacy Begin, OUSD Board of Education …

Pablo Tac Groundbreaking Ceremony Read More »

El Camino High School Locker Room Roof & Mechanical Upgrades

octubre 12, 2021

Scope: Replacement of roofing that is at or past its expected lifespan and perform mechanical upgrades at the El Camino High School Locker Rooms. Status: Construction El Camino HS Funding Source: Proposition H Project Estimate: $298,175 Project Type: Renovation Delivery Method: Prime Contractor   Construction Start: FALL 2021 Targeted Completion: WINTER 2021

El Camino High School Drama Roofing

marzo 25, 2021

Scope: Replacement of roofing that is at or past its expected lifespan at the Performing Arts Center Drama Room Status: Close-Out El Camino HS Funding Source: Proposition H Project Estimate: $88,500 Project Type: Modernization Delivery Method: Multiple Prime Contractor   Construction Start: SPRING 2021 Targeted Completion: SUMMER 2021