Jefferson Middle School Demo & Abatement

Scope: Demolition of buildings K and H, abatement of building F and associated site work at Jefferson Middle School Status: Complete Jefferson MS Funding Source: Proposition H Project Estimate: $353,000 Project Type: Demolition Delivery Method: Prime Contractor   Construction Start: Summer 2020 Targeted Completion: Fall 2020

Jefferson Middle School Campus Modernization & New Gym/MPR

Scope: The modernization of Jefferson Middle School will consist of the following: • Various building modernization • Required ADA upgrades • Required site infrastructure upgrades • Project interim housing • Exterior improvements and upgrades with special attention to redeveloping a main entry • New construction of gym and multipurpose room with kitchen Status: Planning Phase …

Jefferson Middle School Campus Modernization & New Gym/MPR Read More »