Campuses

Laurel Elementary School Portable Replacement

Scope: This project consists of the replacement of a modular building in the kindergarten compound with a new classroom building in the kinder area and the removal of three small offices. Status: Pre-planning Laurel Elementary School Funding Source: Measure W Project Estimate: $2,000,000.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: TBD Completion:

Laurel Elementary School Portable Replacement Read More »

Lincoln Middle School Portable Replacement

Scope: This project consists of the replacement of six portable classroom buildings with prefabricated classrooms Lincoln Middle School Campus. Status: Pre-planning Lincoln MS Modernization Funding Source: Measure W Project Estimate: $5,000,000.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start: TBD Completion: TBD

Lincoln Middle School Portable Replacement Read More »

El Camino High School Restroom Buildings & Weight Room

Scope: This project consists of the addition of two new restroom buildings and the replacement of the weight room/classroom.  The project also consists of planning for the stadium entryway for possible redesign and ADA compliance. Status: Design phase Funding Source: Measure W Project Estimate: $6,500,000.00 Project Type: New Construction Delivery Method: Multiple-Prime   Construction Start:

El Camino High School Restroom Buildings & Weight Room Read More »

Oceanside High School Bleacher Replacement

Scope: This project consisted of the removal of existing bleachers and replacing them with a new VersaTract telescopic bleacher system. The electrical was updated to meet the requirement of the new bleachers. Status: Complete Oceanside HS Gym Funding Source: Proposition H Project Cost: $566,000.00 Project Type: Renovation Delivery Method: Multi-Prime   Construction Start: Summer 2023

Oceanside High School Bleacher Replacement Read More »

Oceanside High School Track & Field Replacement

Scope: This project will consist of replacement of the replacement of the running track and football field turf on the Oceanside High School Campus.  The project also consists of ADA upgrades. Status: Financial Closeout OHS Field Funding Source: Measure W Project Estimate: $2,150,000.00 Project Type: Modernization Delivery Method: Multiple-Prime   Construction Start: Summer 2023 Targeted

Oceanside High School Track & Field Replacement Read More »

ECHS Track & Field Replacement

Scope: This project will consist of replacement of the replacement of the running track and football field turf on the El Camino High School Campus.  The project also consists of some ADA upgrades. Status: Financial Closeout ECHS field Funding Source: Measure W Project Estimate: $2,150,000.00 Project Type: Modernization Delivery Method: Multiple-Prime   Construction Start: Summer

ECHS Track & Field Replacement Read More »

McAuliffe Elementary School HVAC Replacement

Scope: This project will consist of replacement of various HVAC systems on the McAuliffe Elementary School Campus. Status: Pre-design Phase McAuliffe Elementary School Funding Source: Measure W Project Estimate: $3,000,000.00 Project Type: Modernization Delivery Method: Multiple-Prime   Construction Start: TBD Targeted Completion: TBD

McAuliffe Elementary School HVAC Replacement Read More »

Ivey Ranch Elementary School Roof, HVAC, & Walkways

Scope: This project will consist of replacement of various roof and HVAC systems, along with several covered walkways on the Ivey Ranch Elementary School Campus. Status: Design Phase Ivey Ranch ES Funding Source: Measure W Project Estimate: $7,600,000.00 Project Type: Modernization & New Construction Delivery Method: Multiple-Prime   Construction Start: Summer 2025 Targeted Completion: Winter