Surfside Educational Academy Campus Modernization

Scope:

The modernization of Surfside Educational Academy will consist of the following:
• Upgrades to existing buildings
• Required ADA upgrades
• Required site infrastructure upgrades
• Hardscape and landscape
• Replacement of modulars that have exceeded life expectancy

Status:

Increment 2 procurement and construction

Ditmar ES

Funding Source:

Measure W

Project Estimate:

$27,500,000

Project Type:

Modernization

Delivery Method:

Design Bid Build

Construction Start:

Summer 2024

Targeted Completion:

Winter 2026