Surfside Educational Academy Campus Modernization

Scope:

The modernization of Surfside Educational Academy will consist of the following:
• Upgrades to existing buildings
• Required ADA upgrades
• Required site infrastructure upgrades
• Hardscape and landscape
• Replacement of modulars that have exceeded life expectancy

Status:

Design Phase

Ditmar ES

Funding Source:

Measure W

Project Estimate:

$27,500,000

Project Type:

Modernization

Delivery Method:

Multiple Prime

Construction Start:

Spring 2024

Targeted Completion:

Spring 2027

en_USEnglish
Scroll to Top