Completed December 2019 Demolition of existing asphalt and repaving of parking lot.
Scope: Evaluate and present design alternatives for ADA compliance improvements. Status: Reynolds Elementary School: ADA Compliance Funding Source: Proposition H Project Estimate: TBD Project Type: ADA improvements to buildings and access Delivery Method: TBD Project Phase/Status: TBD Construction Start: TBD Targeted Completion: TBD Program Manager: CCM/MAAS Construction Manager: CCM/MAAS Design Professional:
Scope: Renovate all parking areas, improve access, complete previous work of playground. Status: McAuliffe ES Playground 1 Funding Source: Proposition H Project Estimate: $90,000.00 Project Type: Parking, Road and Site Improvements Delivery Method: Design-Bid-Build Project Phase/Status: TBD Construction Start: Summer 2019 Targeted Completion: Fall 2019 Program Manager: CCM/MAAS Construction Manager: CCM/MAAS Design Professional:
Scope: New Construction of Varsity Softball Field including dugouts, field, and lights. Modernization of existing field for Junior Varsity. Update surrounding area including obstacle course, new landscaping, new fencing, and repair infrastructure to bring the site up to complete ADA Compliance. Status: Complete ECHS SFI Before After Funding Source: Proposition H Project Estimate: $1,427,400.00 Project […]
Scope: The Truax theater project includes an interior update to the lobby and ticket area with new flooring, paint, lighting, ceiling and windows. The auditorium will have new carpet and flooring seal along with a general cleaning. The exterior of the building will receive new paint at the entrance to the theater, new handrails, minor […]
Scope: This project includes the removal of existing bleachers and replacing them with a new VersaTract telescopic bleacher system. The electrical will be updated to meet the requirement of the new bleachers. Status: Close-out Bleacher Versatract Funding Source: Proposition H Project Estimate: $18,000 Project Type: Renovation Delivery Method: Design-Bid-Build Construction Start: Fall 2020 Targeted […]
Scope: The Roof and HVAC project consists of removing and replacing 4 HVAC units for more energy efficient units, replacing the roof membrane that is 25+ years old and associated work including electrical and plumbing. The interior of the gym and lobby will receive a fresh coat of paint and a new logo and a […]
Completed February 2018 In addition to a 502-seat main theater, the PAC includes a black box theater, drama classrooms, recording studio, scene shop, and green room. The indoor-outdoor lobby with its concession area doubles as an event venue, as does the new plaza on the west side of the building. The main theater is equipped […]
Completed August 2017 Turf and ornamental landscaping were added to restore areas graded during 2016 construction. A large bioswale was constructed to retain and filter stormwater. The main electrical service for the campus was upgraded to accommodate increased demand.
Three relocatable classrooms were added to accommodate projected enrollment growth. A new playground with new equipment and safe, accessible surfacing replaced the outdated sand and steel. Nine new parking spaces were added.